Factor Analysis of Time and Cost Overruns in Construction of Irrigation Projects

Vinod Kumar Nayak Deeravath*, Suresh Kumar N.**
*-** Department of Civil Engineering, Osmania University, Hyderabad, Telangana, India.
Periodicity:July - September'2024

Abstract

Most construction projects in Telangana, India, are subject to time and cost overruns. This phenomenon may adversely affect the progress of the construction industry in Telangana, India, and potentially lead to the collapse of many construction organizations. This study focuses on identifying and evaluating the factors contributing to time and cost overruns in construction projects in Telangana, India, specifically in the construction of irrigation projects. To achieve the objectives of this study, initial questionnaire surveys were conducted, followed by factor analysis of time and cost overruns. Approximately ten projects were visited, and data were collected over a span of twenty-two months. The factors causing time and cost overruns in irrigation construction projects in Telangana were categorized into four major groups: manpower-related, machinery-related, equipment-related, and financial-related. These factors were analyzed using Statistical Package for Social Sciences (SPSS) software for factor analysis. Factor analysis was conducted using two distinct approaches: Exploratory Factor Analysis which explores underlying structures without prior hypotheses and Confirmatory Factor Analysis (CFA) which tests a pre-specified model, requiring prior knowledge. EFA and CFA are complementary techniques for understanding the underlying structure of a set of variables. CFA can refine the factor structure suggested by EFA. The combined results from these analyses contribute to the development of reliable and valid measurement scales.

Keywords

Telangana Construction Industry, Time Overrun, Cost Overrun, Pilot Survey, Questionnaire, SPSS, Factor Analysis, Exploratory Factor Analysis (EFA), Confirmatory Factor Analysis (CFA).

How to Cite this Article?

Deeravath, V. K. N., and Kumar, N. S. (2024). Factor Analysis of Time and Cost Overruns in Construction of Irrigation Projects. i-manager’s Journal on Civil Engineering, 14(3), 1-24.

References

[2]. Ameh, O. J., & Osegbo, E. E. (2011). Study of relationship between time overrun and productivity on construction sites. International Journal of Construction Supply Chain Management, 1(1), 56-67.
[7]. Hair JR, J. F., Black, W. C., Babin, B. J., & Anderson, R. E. (2010). Multivariate Data Analysis: A Global Perspective. Pearson.
[11]. Kline, R. B. (2023). Principles and Practice of Structural Equation Modeling. Guilford Publications.
[18]. McClave, J. T. (2018). Statistics for Business and Economics. Pearson, Boston.
[20]. Morris, S. (1990). Cost and time overruns in public sector projects. Economic and Political Weekly, 25 (47), M154-M168.
[21]. Morris, S. (1990). Cost and time overruns in public sector projects. Economic and Political Weekly, 25 (47), M154-M168.
[24]. Salunkhe, A. A., & Patil, R. S. (2014). Effect of construction delays on project time overrun: Indian scenario. International Journal of Research in Engineering and Technology, 3(1), 543-547.
[27]. Sanders, D., & Eagles, W. D. (2001). Delay, Disruption and Acceleration Claims. Borden Ladner Gervais LLP.
[29]. Singh, R. (2010). Delays and cost overruns in infrastructure projects: Extent, causes and remedies. Economic and Political Weekly, 45 (21), 43-54.
If you have access to this article please login to view the article or kindly login to purchase the article

Purchase Instant Access

Single Article

North Americas,UK,
Middle East,Europe
India Rest of world
USD EUR INR USD-ROW
Online 15 15

Options for accessing this content:
  • If you would like institutional access to this content, please recommend the title to your librarian.
    Library Recommendation Form
  • If you already have i-manager's user account: Login above and proceed to purchase the article.
  • New Users: Please register, then proceed to purchase the article.