Enhancing Profitability through Improved Material Management Practices in Construction Projects

K. N. Narasimha Prasad*, Shreyas M. V.**, Akash Deshpande***, Rohit Singh****
* Associate Professor, National Institute of Construction Management and Research, Goa Campus, Goa, India.
** Management Trainee, AFCONS Infrastructure Limited, Andheri (West), Mumbai, Maharashtra, India.
*** Post-graduate Engineer Trainee, L&T Constructions, Mumbai, Maharashtra, India.
**** Senior Engineer, Montecarlo Limited, Kendujhar, Odisha, India.
Periodicity:September - November'2018
DOI : https://doi.org/10.26634/jce.8.4.14451

Abstract

Efficient material management can turn a construction project into a profit centre from a cost centre if rational material classification, inventory management and economical order quantity practices are followed. Most construction companies in India do not appear to have such practices in place. In this work, the benefits of efficient material management practices are discussed and a case study of material procurement schedule in a precast infrastructure company is made. The results indicate that materials were procured without any analysis with reference to their importance, inventory cost control, pre-plan for using available storage space efficiently, seasonality and other critical factors necessary to ensure smooth progress of the work. The study also reveals the need for developing material management practices designed for construction sites. In conclusion, the paper suggests the importance of following efficient material management practices in construction projects and the need to develop new material management practices suitable for construction sites considering its dynamics and constraints.

Keywords

Material management, inventory control, material handling, purchase

How to Cite this Article?

Prasad, K. N. N., Shreyas, M. V., Deshpande, A., & Singh, R. (2018). Enhancing Profitability Through Improved Material Management Practices in Construction Projectsi-manager's Journal on Civil Engineering, 8(4), 13-20. https://doi.org/10.26634/jce.8.4.14451

References

[1]. Anil Kumar, C. N., Sakthivel, M., Elangovan, R. K., & Arularasu, M. (2015). Analysis of material handling safety in construction sites and countermeasures for effective enhancement. The Scientific World Journal, 2015, 1-7. doi: 10.1155/2015/742084
[2]. Agapiou, A., Clausen, L. E., Flanagan, R, Norman, G., & Notman, D. (1998). The role of logistics in the materials flow control. Construction Management and Economics, 16(2), 131-137.
[3]. Agrawal, V. M., Krishna, M. N., & Pattanaik, J. (2018). Incorporation of effective safety management system in construction industry with defined responsibility of management. i-manager's Journal on Civil Engineering, 8(2), 1-6.
[4]. Chaffey, D. (2009). E-Business and E-Commerce Management, Strategy, Implementation & Practice, (2nd Ed) Prentice Hall.
[5]. Datta, A. K. (2012). Material Management: Procedures, Text and Cases (2nd Ed.). New Delhi: PHI Learning.
[6]. Dey, P. K. (2000). Managing projects in fast track – A case of public sector organisation in India. International Journal of Public Sector Management, 13(7), 20-29.
[7]. Formoso, C. T., Soibelman, L., De Cesare, C., & Isatto, E. L. (2002). Materials waste in building industry: Main causes and prevention. Journal of Construction Engineering and Management, 128(4), 316-325.
[8]. Illingworth, J. R. (2000). Construction Methods and Planning (2nd Ed.). Boca Raton. CRC Press.
[9]. Kasim, N. B., & Ang, S. E. P. (2010). The awareness of ICT implementation for materials management in construction projects. International Journal of Computer and Communication Technology, 2(1), 1-10.
[10]. Kasim, N. B., Anumba, C. J., & Dainty, A. R. J. (2005). Improving materials management practices on fast-track construction projects. 21st Annual ARCOM Conference, (Vol. 2, pp. 793-802).
[11]. Kent, T. (1991). In Guidelines for the Management of Major Construction Projects, NEDC, HMSO, London.
[12]. Kini, D. U. (1999). Material management: The key to successful project management'. Journal of Management in Engineering, ASCE, 15(1), 30-34.
[13]. Mcdonald, B., & Smithers, M. (1998). Implementing a waste management plan during the construction phase of a project: A case study. Construction Management & Economics, 16(1), 71-78
[14]. Nanaware, M. R., & Saharkar, U. R. (2017). Applications of Inventor y Control Techniques in Construction. International Journal of Engineering Research and General Science, 5(4), 49-54.
[15]. NICMAR Centre of Distance Education. (1998). NCB- 49, Construction Materials Management – Lesson Book. Mumbai, India, NICMAR Publication Bureau.
[16]. Ogunlana, S. O., Promkuntong,K., & Jearkjirm, V. (1996). Construction delays in a fast-growing economy: Comparing Thailand with other economies. International Journal of Public Sector Management, 14(1), 37-45.
[17]. Patel, C. H., Chaturvedhi, H., Megha, R. R., Katta, P., & Narasimha Prasad, K. N. (2015). An analysis of cost and time overruns in construction projects. NICMAR Journal of Construction Management, 30(2), 37-50.
[18]. Patel, K. V., & Vyas, C. M. (2011, May). Construction materials management on project sites. In National Conference on Recent Trends in Engineering & Technology (pp. 1-5).
[19]. Pheng, L. S., & Chuan, C. J. (2001). Just-in-time management in precast concrete construction: A survey of the readiness of main contractors in Singapore. Integrated Manufacturing Systems, 12(6), 416-429.
[20]. Rathod, A., & Pimplikar, S. S. (2013). Delays in residential building construction. International Journal of Innovative Research & Development, 2(5), 1908-1922.
[21]. Stukhart, G. (1995). Construction Materials Management. New York, USA, Marcel Dekker Inc.
[22]. Teo, M. M. M., & Loosemore, M. (2001). A theory of waste behavior in the construction industry. Construction Management and Economics, 19(7), 741-751.
[23]. Tommelein, I. D. (1994). Materials handling and site layout control. 1994 Proceedings of the 11th ISARC (pp. 297- 304). https://doi.org/10.1016/B978-0-444-82044-0.50044- 8
[24]. Wilfred, A., Deepak, M. D., Shivaram, N., Nataraj, M., & Khan, Y. (2015). An empirical study of material management in residential project. International Research Journal of Engineering and Technology, 2(4), 1116-1119.
[25]. Zeb, A., & Khattak, S. B. (2017). Inventory analysis of construction industry. Proceedings of the First International Conference on Industrial Engineering and Management Applications (pp. 68-81).
If you have access to this article please login to view the article or kindly login to purchase the article

Purchase Instant Access

Single Article

North Americas,UK,
Middle East,Europe
India Rest of world
USD EUR INR USD-ROW
Pdf 35 35 200 20
Online 35 35 200 15
Pdf & Online 35 35 400 25

Options for accessing this content:
  • If you would like institutional access to this content, please recommend the title to your librarian.
    Library Recommendation Form
  • If you already have i-manager's user account: Login above and proceed to purchase the article.
  • New Users: Please register, then proceed to purchase the article.